C H A P T E R  2

Site Planning

This chapter outlines the site-planning requirements and basic safety requirements for the installation and use of the Sun StorEdge 3510 FC Array. Complete a preinstallation worksheet and prepare the site for installation according to the worksheet details and the specified site-planning requirements.

Review the details of this chapter before installing a Sun StorEdge 3510 FC Array. Topics covered in this chapter are:



Note - The release notes for your array list the supported operating environments, host platforms, software, and qualified cabinets.




2.1 Customer Obligations

The customer is obliged to inform Sun Microsystems, Inc. of any and all ordinances and regulations that would affect installation.



caution icon

Caution - When selecting an installation site for the Sun StorEdge 3510 FC Array, choose a location that avoids excessive heat, direct sunlight, dust, or chemical exposure. Such exposure greatly reduces the product's longevity and might void your warranty.



The customer is responsible for meeting all government codes and regulations concerning facilities. The customer is also responsible for compliance with the following requirements:


2.2 Safety Precautions

For your protection, observe the following safety precautions when setting up your equipment:


2.3 Environmental Requirements

TABLE 2-1 Environmental Specifications

Operating

Nonoperating

Altitude

To 3000 meters (9000 feet)

To 12,000 meters (36,000 feet)

Humidity

10% to 90% RH at 27 degrees C max wet bulb (noncondensing)

93% RH, 38 degrees C max wet bulb temperature (noncondensing)

Temperature

Standalone

Rack

 

5 degrees C to 40 degrees C

5 degrees C to 35 degrees C

 

-40 degrees C to +65 degrees C

-40 degrees C to +65 degrees C


2.3.1 Electromagnetic Compatibility (EMC)

The following is required for all installations:


2.4 Electrical and Power Specifications

The Sun StorEdge 3510 FC Array requires two independent power sources. Each array has two power supply and fan modules for redundancy.

Each AC array requires two 115 VAC/15A or two 240 VAC service outlets. All AC power supplies are autoranging and are automatically configured to a range of 90-264 VAC and 47-63 Hz. There is no need to make special adjustments.

Each DC array requires two -48 VDC service outlets and has an input voltage range of -36 VDC to -72 VDC.



Note - To ensure power redundancy, be sure to connect the two Sun StorEdge 3510 FC power modules to two separate circuits (for example, one commercial circuit and one UPS).



TABLE 2-2 Power Specifications

AC power

Voltage and frequency 90 to 264 VAC, 47 to 63 Hz

Input current

5A max

Power-supply output voltage

+5 VDC and +12 VDC

DC power

-48V DC (-36 VDC to -72 VDC)



2.5 Physical Specifications

Use the physical specifications in TABLE 2-3 to plan the location of your array.

TABLE 2-3 Physical Specifications

Category

Description

Dimensions

2U (3.45 inches / 8.76 cm) height

20 inches / 50.8 cm chassis depth

17.5 inches / 44.6 cm width (19 inches / 48.26 cm with ears)

Installation clearances

For FRU component removal and replacement, 15-inches (37 cm) is required front and back.

Cooling clearances

6 inches (15 cm) is required front and back. No cooling clearance is required on the sides or the top and bottom of the array.



2.6 Layout Map

It is helpful to create a sketch or layout map to indicate the exact location for the Sun StorEdge 3510 FC Array as well as the location of the hosts, console, and Ethernet connections that will be connected to it.

As you lay out the components, consider the cable lengths that will be used.

2.6.1 Rack Placement

Follow these guidelines when preparing a rackmount placement for your system:

2.6.2 Tabletop Placement

The Sun StorEdge 3510 FC Array can be positioned on a desk or a table. Follow these guidelines when preparing a tabletop placement for your system:


2.7 Console and Other Requirements

A console with at least one serial port or Ethernet connection is necessary for installation and configuration of your Sun StorEdge 3510 FC Array. Once you have configured your array with an IP address, the Ethernet port can also be useful for configuring the array.

Refer to the following preinstallation worksheet for additional preparation details.


2.8 Preinstallation Worksheet

Before ordering a Sun StorEdge 3510 FC Array, complete the preinstallation worksheet and then prepare the site for installation according to the site-planning requirements.



Note - If you are connecting to several hosts or Fabric switches, make as many copies of TABLE 2-5 as you need and label them appropriately.



You are responsible for ensuring that the site consistently conforms to all stipulated standards and that necessary peripherals are made available to the engineer during installation.

Review the details of your specific survey before installing your Sun StorEdge 3510 FC Array.

If necessary, attach or sketch a network diagram to the survey.

TABLE 2-4 Preinstallation Worksheet

Rackmounting

 

Customers must ensure that the appropriate service outlets are available for installation. Requirements vary.

Will the Sun StorEdge 3510 FC Array be rackmounted? Yes / No

  • Is the rack supplied by Sun Microsystems, Inc.? Yes / No
  • If yes, include Sun model number: ____
  • If not, make/model: _____________________ / _____________________

Does the rack mount:

  • Front and back? If so, depth? ______
  • Center/Telco? ______

What cable lengths are required? _________________

Are there any power strips or power sequencers in the rack? Yes / No

Are they supplied by Sun Microsystems, Inc.? Yes / No If yes, part number: ___________

If not, quantity of plugs/outlets required: __________ / __________

 

IP address

 

Array IP address: ______.______.______.______

Array network mask: ______.______.______.______

 

Cabling

 

FC cable lengths to connect to hosts: _______________

 


TABLE 2-5 Host and Fabric Switch Connectivity Summarized

Host or Fabric Switch Connectivity - Host or Fabric Switch #1

Host or Fabric switch name: _____________________________________

 

Host or Fabric switch make/model: ________________________________

 

HBA connector types: _____________________________

 

Cable distance from the array to the host(s): ___________

 

Operating environment: ________________________________

 

Patches installed: ________________________________

 

IP addresses:

  • Network ____________________
  • Host or switch _______________

 

 

 

Host or Fabric Switch Connectivity - Host or Fabric Switch #2

Host or Fabric switch name: _____________________________________

 

Host or Fabric switch make/model: ________________________________

 

HBA connector types: _____________________________

 

Cable distance from the array to the host(s): ___________

 

Operating environment: ________________________________

 

Patches installed: ________________________________

 

IP addresses:

  • Network ____________________
  • Host or switch _______________