C H A P T E R  6

Site Planning Checklist

TABLE 6-1 organizes the site planning tasks into a checklist that you can use during the site planning process.

TABLE 6-1 Site Planning Checklist

Requirement

Completed

Task

Configuration

Yes__No__

Have you determined the hardware configuration for each system?

 

Yes__No__

Have you determined the type and number of cabinets and racks you need?

 

Yes__No__

Have you determined how you will populate each rack?

 

Yes__No__

Have you determined which external peripherals, such as terminals, monitors, keyboards, SCSI devices, and so forth, the systems require?

Environmental

Yes__No__

Does the data center environment meet the system specifications for temperature and humidity?

 

Yes__No__

Have you determined the thermal load, heat dissipation, and air conditioning requirements of all equipment in the data center?

 

Yes__No__

Can you maintain the data center environment when certain failures occur, such as power failure, air conditioning unit failure, or humidity control unit failure?

 

Yes__No__

Is fire suppression and alarm equipment installed?

Power

Yes__No__

Have you determined the maximum power requirements of the systems?

 

Yes__No__

Have you considered using an alternate source of power for grid independence and backup power for the local sub-station?

 

Yes__No__

Have you installed a UPS?

 

Yes__No__

Do you have sufficient power receptacles and circuit breakers for each system and its peripherals?

 

Yes__No__

Are the power receptacles within 15 feet (4.6 m) of the racks or within 6 feet (1.8 m) of a standalone system?

 

Yes__No__

Have you installed and labeled the circuit breakers?

Physical

Yes__No__

Does the facility's loading dock meet standard common carrier truck requirements? If not, have you made other arrangements for unloading the racks and systems, such as providing a fork lift?

 

Yes__No__

Are pallet jacks or carts available to move the systems and racks from the loading dock to the computer room?

 

Yes__No__

Will the equipment fit through the access route and into the computer room?

 

Yes__No__

Have you calculated the weight of each rack with all the equipment installed within it?

 

Yes__No__

Is the data center floor able to support the weight of the systems and racks?

 

Yes__No__

Have you established where you will locate each rack on the data center floor?

 

Yes__No__

Are the systems and racks positioned so that the heated exhaust air of one system does not enter the air inlet of another system?

 

Yes__No__

Is there sufficient room around the racks for system access and maintenance?

Miscellaneous

 

Yes__No__

Are there sufficient number of people available to unload, unpack, and install the systems into the racks?

 

Yes__No__

Have system administrators and service technicians enrolled in appropriate training courses to upgrade their skills, as necessary?

 

Yes__No__

Have you acquired all the hardware needed to set up the systems and racks?

 

Yes__No__

Do you have the documents required to install the systems into the racks?